Mine engineering quality accident handling procedures

After the project quality accident occurs, it can generally be processed according to the following procedures:
1. When a quality defect or accident occurs in the project, the supervision engineer or the quality management department shall first notify the construction unit in the form of a "quality notice" and request to stop the construction of the quality defect and the expected related parts and the next process. The construction unit should also be required to take protective measures when needed. At the same time, it should be reported to the competent authorities in a timely manner. When the construction unit discovers that a quality accident has occurred, it shall immediately stop the construction of the relevant parts and immediately report to the supervision engineer (construction unit) and the quality management department.
2. After receiving the quality notice, the construction unit shall, under the organization and participation of the supervision engineer, conduct a quality accident investigation as soon as possible and write a report on the quality accident.
3. Based on the accident investigation, analyze the cause of the accident and correctly determine the cause of the accident. The cause analysis of the accident is the basis of the accident handling measures. The supervision engineer should organize the design, construction, construction unit and other parties to participate in the analysis of the cause of the accident.
4. Based on the analysis of the cause of the accident, study and formulate the accident handling plan.
5. After determining the treatment plan, the supervision engineer instructs the construction unit to implement the treatment of quality defects according to the established treatment plan.
6. After the quality defects have been processed, the supervision engineer shall organize the relevant personnel to carry out strict inspection, appraisal and acceptance of the results of the treatment, write a "quality accident handling report", submit it to the owner or construction unit, and report it to the relevant competent department.