This standard specifies the working capacity, responsibility, authority and operating procedures of the cone crusher .
2. area
This standard applies to the operator of the cone position and its inspection and assessment.
3 job ability requirements
3.1 Those who have passed the training of the post and the third-level safety education.
3.2 Have a junior high school education or above.
3.3 Familiar with the working principle of the equipment operated by this post and its safe operation procedures.
4 Responsibility
4.1 Responsible for its own safety.
4.2 Responsible for the safety supervision of non-employees who enter this position.
4.3 Responsible for the safe operation of electromechanical equipment in this position.
4.4 Responsible for the fastening, lubrication and maintenance of the equipment.
4.5 Responsible for the discharge requirements of TC84S/C and TC84SH/F cone crushers .
4.6 Responsible for the cleaning of this position.
5 permissions
5.1 The right to prevent non-employee staff from entering the work area.
5.2 The right to prevent employees who are not wearing protective products from entering the work area.
5.3 Have the right to prevent illegal command and illegal operation.
6 indicator requirements
6.1 TC84SH/F ore discharge particle size requirement is less than 14mm,
7.1 Â Dangerous source of this position
7.1.1 Potential ore flying out of the workshop area.
7.1.2 The dust removal measures of the cone crusher are not perfect, the post dust is too large or the operator is negligent to wear the dust mask.
7.1.3 The post noise is too large or the operator is negligent in wearing anti-noise earplugs.
7.1.4 Upper and lower three-dimensional cross work, round grinding and belt potential ore collapsing and rolling down to the lower platform; and broken ore potential collapses out of the crushing cavity, and the operator does not wear a helmet or helmet is not standardized wear.
7.1.5 The operator does not operate according to the operating procedures. For example, during the operation of the crusher, open the observation hole and observe the operation of the crusher; change the setting values ​​of the automatic control system at will; go to work after drinking.
7.1.6 The motor grounding wire is not connected to zero or the grounding wire is disconnected, or the safety protection device—the microcomputer is integrated.
7.1.7 During the operation of the cone crusher, when the ore does not fall in the crushing chamber and the iron hook is used to make it fall, the potential iron hook is on the operator after the mine has rebounded on the iron hook.
7.2 Safety precautions and control measures
7.2.1 Carefully observe the surrounding environment, beware of the ore flying out
7.2.2 Take precautions against dust hazards, wear dust masks during work, and turn on water spray and dust removal facilities.
7.2.3 Take precautions against noise hazards and wear anti-noise earplugs during work.
7.2.4 Regularly check the integrity of the protective railings and their stairways, and beware of falling down and falling from high places.
7.2.5 Wear labor protection products in strict accordance with the requirements, standardize wearing safety helmets, and beware of ore bruises.
7.2.6 Strengthen business learning, put an end to unsafe behaviors, and operate in strict accordance with the operating procedures.
7.2.7 Attention and careful inspection of the zero connection of the motor, the grounding wire and the protective cover and its high-voltage cable are in good condition at any time. The damage should be repaired in time to ensure the safety of the object.
7.2.8 Actively put an end to unsafe behaviors, and should adhere to regularity and achieve standardized operations. When using iron hook stones, it should be firmly grasped, grasped with iron hooks or should be shut down.
7.3 Environmental factors of this post
7.3.1 Noise generated during equipment operation and crushing.
7.3.2 Dust and raw material dust formed during the crushing process.
7.3.3 Equipment oil leakage.
7.3.4 Leakage and leakage of powder formed by the wear of equipment components.
7.3.5 The water pipe in the workplace is leaking, and the water in the post is not cleaned up in time.
7.3.6 Waste materials are not cleaned up in time.
7.3.7 Equipment and environmental sanitation are not cleaned.
7.4 Environmental Considerations and Control Measures
7.4.1 Take precautions against noise hazards and wear anti-noise earplugs during work.
7.4.2 Take precautions against dust hazards, wear dust masks during work, and open dust removal facilities to ensure proper operation of the dust removal system.
7.4.3 Strengthen the maintenance of the equipment and timely handle the oil spill.
7.4.4 Dispose of and replace worn parts and equipment, and timely clean up leakage and leakage.
7.4.5 Deal with pipeline leaks and post water in a timely manner.
7.4.6 Clean up the waste materials in time and classify them in a centralized manner.
7.4.7 Do a good job in equipment and environmental sanitation.
8.5 Operating procedures
8.5.1 This position must be operated by the shift monitor to operate the main equipment:
a. TC84S/C broken cone crusher, the first to give the largest size of the mine: 300mm, the size of the discharge port: 45 mm.
b. TC84SH/F fine crusher cone crusher, the first size of the mine is first: 80 mm, and the size of the discharge port is 10 mm.
8.5.2 Check before driving:
a. Body part: Whether the bolts of each part are fastened, whether there is oil leakage in the lock cylinder and the outer fuse cylinder of the machine body, whether the umbrella plate is loose or severely worn, the tension of the V-belt and the presence or absence of breakage, turning back, broken There is no ore in the cavity.
b. Electrical part: Whether the electronic control system is normal, whether the alarm system is normal, and whether the ammeter is zero.
c. Lubrication part: Whether the oil level of the thin oil station is sufficient, whether the oil leaks, whether the lubricating oil has deteriorated, and whether the opening of each valve is suitable. Start the oil pump and check whether the oil difference in the lubrication system is normal. The pressure of the oil supply pipe is in the range of 0.5-1.5kgf/cm2, and the oil return temperature should not exceed 500C.
8.5.3 When driving, it must be started without load. After confirming that everything is normal, you can contact the feeding.
8.5.4 Inspection and maintenance during operation, once every 30 minutes, find problems and deal with them in time.
a. Oil supply pressure: 0.5-1.5kgf/cm2, return oil temperature is less than 550C.
b. Each crusher feed should be evenly dispersed in the crushing chamber through the distribution plate, and should not be lower than the horizontal plane of the rolling wall.
c. Always check the pressure of the locking system and the operation of the hydraulic station.
d Check the main system pressure gauge, the normal is 0.05-0.15Mpa
e. Always check the air venting cover to keep it open.
f. Body vibration and adjustment ring runout.
8.5.5 Check and clean the oil filter regularly.
8.5.6 When parking, the ore in the cavity of the crusher is empty and the host is stopped, and finally the oil station is stopped. In case of special circumstances, manually clean the ore in the crushing chamber for the next start.
8.5.7 Do the lubrication of the following equipment:
China Household And Industrial Mould,Cube Mold manufacturer, choose the high quality Plastic Molding,Plastic Injection Molding, etc.
Pipe Fitting Mould,Pvc Pipe Fitting Mould,Pipe Injection Molding,Fitting Mould
Taizhou Zijing Plastic and Mould Co.,Ltd. , https://www.zijingmould.com